South Carolina Mechanics Lien Law

Everything you need to know to protect your lien rights in South Carolina

Critical Deadlines

90

days - Preliminary Notice

90

days - Lien Filing

180

days - Enforcement

📋Preliminary Notice

REQUIRED
Deadline
90 days from first furnishing
Form Name
Notice of Project Commencement
Must be Served To
Owner, Lender
Delivery Method
Certified mail

Warning: Missing this deadline may result in losing ALL lien rights.

⚖️Lien Filing

Filing Deadline
90 days from last work
Where to File
Register of Deeds/Clerk of Court
Filing Fee
$15-35
Description
Within 90 days of last furnishing

⏱️Enforcement

Deadline to Sue
180 days from filing lien
Description
Within 6 months of filing lien

Note: If you don't file a lawsuit within this period, your lien becomes unenforceable.

🏛️Public Projects (Bond Claims)

Preliminary Notice
Required within 90 days
Bond Claim Deadline
90 days from completion
Governing Statute
SC Code §29-6

Special Rules & Contractor Protections

Pay-if-Paid

⚠️ Enforceable

Anti-Indemnity

✓ Protected by SC Code §32-2-10

Prompt Payment

21 days

License Required

⚠️ Yes - unlicensed may lose lien rights

💡 Important Notes for South Carolina

  • 90-day notice required

📚 Statute References

Lien Law:
SC Code §29-5-10
Bond Law:
SC Code §29-6
Prompt Pay:
SC Code §29-6

Protect Your Rights in South Carolina

SubShield automatically applies South Carolina lien laws when analyzing your contracts. Get deadline tracking, compliance alerts, and personalized risk analysis.

This information is for educational purposes only and is current as of January 2026. Always consult with a licensed South Carolina construction attorney for your specific situation.