Mississippi Mechanics Lien Law

Everything you need to know to protect your lien rights in Mississippi

Critical Deadlines

30

days - Preliminary Notice

90

days - Lien Filing

360

days - Enforcement

📋Preliminary Notice

REQUIRED
Deadline
30 days from first furnishing
Form Name
Stop Notice
Must be Served To
Owner
Delivery Method
Registered mail

Warning: Missing this deadline may result in losing ALL lien rights.

⚖️Lien Filing

Filing Deadline
90 days from last work
Where to File
Chancery Clerk
Filing Fee
$20-35
Description
Within 90 days of last furnishing

⏱️Enforcement

Deadline to Sue
360 days from filing lien
Description
Within 1 year of filing lien

Note: If you don't file a lawsuit within this period, your lien becomes unenforceable.

🏛️Public Projects (Bond Claims)

Preliminary Notice
Required within 90 days
Bond Claim Deadline
90 days from completion
Governing Statute
Miss. Code Ann. §31-5-51

Special Rules & Contractor Protections

Pay-if-Paid

⚠️ Enforceable

Anti-Indemnity

✓ Protected by Miss. Code Ann. §31-5-41

Retainage Cap

5%

License Required

⚠️ Yes - unlicensed may lose lien rights

💡 Important Notes for Mississippi

  • Stop Notice is the preliminary notice term in Mississippi

📚 Statute References

Lien Law:
Miss. Code Ann. §85-7-131
Bond Law:
Miss. Code Ann. §31-5-51

Protect Your Rights in Mississippi

SubShield automatically applies Mississippi lien laws when analyzing your contracts. Get deadline tracking, compliance alerts, and personalized risk analysis.

This information is for educational purposes only and is current as of January 2026. Always consult with a licensed Mississippi construction attorney for your specific situation.