🔥 Limited Time:First analysis FREE (usually $47)
23:45:00
Claim Now
📚 Free Resource

Contract Clause Library

Reference guide to risky contract clauses with discussion points you can customize and use.

Payment

Pay-If-Paid

CRITICAL

Payment conditioned on owner payment to GC. You bear collection risk.

Dangerous Language

""Payment to Subcontractor is expressly conditioned upon receipt by Contractor of payment from Owner...""

Recommended Language

""Payment shall be made within 30 days of approved invoice. Payment timing may be adjusted based on Owner payment but shall not exceed 45 days regardless of payment status from Owner.""

Discussion Points

We request modifying this to a pay-when-paid clause with a 45-day outside date. This protects both parties while aligning with ConsensusDocs 750 standards.

Payment

Pay-When-Paid

WARNING

Payment timing tied to owner payment, but not a condition precedent.

Dangerous Language

""Payment within 10 days of receipt of payment from Owner...""

Recommended Language

""Payment within 30 days of receipt of payment from Owner, but in no event later than 60 days from approved invoice regardless of payment status from Owner.""

Discussion Points

Please add an outside date of 60 days. This creates a reasonable backstop while respecting the payment flow.

Payment

High Retainage

WARNING

Retainage above the 5% industry standard ties up your working capital.

Dangerous Language

""Contractor shall retain ten percent (10%) of each progress payment...""

Recommended Language

""Contractor shall retain five percent (5%) of each progress payment. Retainage shall be reduced to 2.5% upon 50% completion of Subcontractor's scope.""

Discussion Points

The 10% retainage exceeds industry standard. We request reducing to 5% with early release provisions.

Liability

Broad Form Indemnification

CRITICAL

You may be liable for damages even when the GC is at fault.

Dangerous Language

""Subcontractor shall indemnify, defend, and hold harmless Contractor from ANY claims... regardless of whether caused by Contractor's negligence...""

Recommended Language

""Subcontractor shall indemnify Contractor to the extent claims arise from Subcontractor's negligent acts or omissions, but not for claims arising from the negligence of Contractor or others.""

Discussion Points

This broad form indemnification conflicts with [State] anti-indemnity statutes. Please modify to comparative fault indemnification per AIA A201.

Liability

Unlimited Liability

CRITICAL

No cap on your potential liability exposure.

Dangerous Language

""Subcontractor shall be liable for all damages, costs, and expenses arising from the Work...""

Recommended Language

""Subcontractor's total liability shall not exceed the Contract Sum, excluding claims covered by insurance.""

Discussion Points

We request adding a liability cap equal to the contract value. This is standard practice for professional service agreements.

Schedule & Delays

No-Damage-For-Delay

WARNING

You waive the right to recover costs from GC-caused delays.

Dangerous Language

""Subcontractor waives all claims for damages for delays caused by any reason whatsoever...""

Recommended Language

""Subcontractor waives claims for delay damages except for: (1) active interference by Contractor, (2) delays not contemplated by the parties, or (3) Contractor's breach of contract.""

Discussion Points

We request adding standard exceptions to the no-damage-for-delay clause as permitted by courts in most jurisdictions.

Schedule & Delays

Liquidated Damages Flow-Down

WARNING

GC passes owner's liquidated damages to you without proportional allocation.

Dangerous Language

""Subcontractor shall be liable for all liquidated damages assessed against Contractor by Owner that are attributable to Subcontractor's Work...""

Recommended Language

""Subcontractor's share of any liquidated damages shall be proportional to Subcontractor's contribution to the delay, as documented, and shall not exceed [specific cap].""

Discussion Points

We request capping LD exposure and requiring proportional allocation based on documented delay contribution.

Warranty

Extended Warranty

CAUTION

Warranty period exceeds the 1-year industry standard.

Dangerous Language

""Subcontractor warrants all Work for two (2) years from Final Completion of the Project...""

Recommended Language

""Subcontractor warrants the Work for one (1) year from Subcontractor's substantial completion, or the manufacturer warranty period, whichever is longer.""

Discussion Points

The extended warranty exceeds industry standard. We request aligning with AIA A201's one-year warranty from our substantial completion.

Lien Rights

Unconditional Lien Waiver Before Payment

CRITICAL

You waive lien rights before receiving cleared payment.

Dangerous Language

""Subcontractor shall provide an unconditional lien waiver for all work prior to receiving each progress payment...""

Recommended Language

""Subcontractor shall provide conditional lien waivers with payment applications. Unconditional waivers shall be provided upon receipt of cleared funds.""

Discussion Points

We will provide conditional waivers upon application and unconditional waivers upon receipt of cleared funds. This protects our statutory lien rights.

Change Orders

Strict Written Change Order Requirement

WARNING

No compensation for verbal directives or constructive changes.

Dangerous Language

""No claim for extra work shall be valid unless authorized by a written change order signed by Contractor prior to commencement of such work...""

Recommended Language

""Verbal directives for changes shall be confirmed in writing by Contractor within 3 business days. Constructive changes directed by field personnel shall be compensable upon Subcontractor's written notice.""

Discussion Points

Please add a mechanism for confirming verbal directives in the field. This is essential for practical project management.

Let AI Find These Clauses For You

Upload your contract and SubShield will automatically identify risky clauses with customized discussion points.

Analyze Your Contract →